US Geothermal (HTM) Provides Operation Updates
US Geothermal (HTM) has provided updates on its geothermal operations in several locations.
===> Click Here For Your FREE US Geothermal Technical Analysis
Neal Springs
- an injection well has been drilled to 2465 feet and successfully tested
- a 2nd well at 1950 is expected to be completed within a week or two
- a production well at 2350 feet expected to reach production within a couple weeks
- equipment procurement and pipeline fabrication underway to prepare for 30 day reservoir test to begin mid Oct
San Emidio Phase 1
- construction underway on 11.5MW modular plant
San Emideo Phase 2
- exploration and geological mapping underway
- data acquisition expected to be completed by mid Oct and processing completed by mid Nov
- complete analysis to determine drill targets by year end
Raft River
- $10.2 million DOE cost shared fracturing program continuing on schedule
- construction nearly complete on injection pipeline from unit 1 plant to well rrg-9
- first phase of cold water injection will commence early 2011
Gerlach (HTM owns 60%)
- final planning and drill bid evaluation underway for production well drilling expected to begin in a few weeks
- five separate potential production zones identified but not tested yet
- Gerlach ranked the 3rd best geothermal resource in Nevada by US Geological Survey
Sep.22
I still like NGLPF.ob for the bang for the Buck